1 |
To Carwyn Jones AM, Counsel General, National Assembly for
Wales, Cardiff Bay CF99 1NA |
|
2 |
The claimant David Firth. A
trustee of the Snowdonia Society (and Chairman), Ty Hyll, Capel Curig, Conwy
LL24 ADS. The Society,
established 40 years ago and now with over 2500 members, is a registered
charity (number 253231) which seeks to protect the landscape, wildlife and
cultural heritage of Snowdonia for the benefit of those who live in or visit
the National Park, and for future generations. |
|
3 |
Reference details Welsh Ministers’ decision on land in public ownership at the
disused and decommissioned former RAF Llanbedr Airfield, Gwynedd (CYM304057) as announced on
February 25, 2008. |
|
4 |
The details of the matter being challenged The decision of Welsh Ministers to grant a 125 year lease at
Llanbedr, Gwynedd to Kemble Air Services in order to create a commercial
airfield in the Snowdonia National Park. |
|
5 |
The issue The failure of Welsh Ministers to “have regard” to the
“statutory purposes” of the Snowdonia National Park as required by Section 62
of the Environment Act 1995 before exercising their functions in relation to
land in their control. The first statutory purpose of the Snowdonia National Park is
defined in s61 as “conserving and enhancing the natural beauty, wildlife and
cultural heritage”. The second purpose is “ promoting opportunities for the
understanding and enjoyment of the special qualities of those areas by the
public”. In the event of conflict the first purpose has “greater weight”. Since March 3, The Society has been attempting to seek
confirmation that Welsh Ministers have acted lawfully by several Freedom of
Information Act requests to see evidence.
This information has not been supplied. |
|
6 |
The details of the action that the defendant is expected to take Suspension of the lease process and a full re-consideration of
potential future use of the site taking into account the duty placed upon
Welsh Ministers by Section 62. An undertaking not to proceed with the lease signing until this
matter is resolved. We may seek an injunction. |
|
7 |
The details of the legal advisers, if any, dealing with this
claim
To be advised. |
|
8 |
The details of any interested parties A copy of this letter has been sent to the Snowdonia National
Park Authority and Kemble Air Services Ltd |
|
9 |
The details of any information sought An explanation of how Welsh Ministers have considered and
discharged their s 62 legal duty. Despite several written requests this has
not been provided. |
|
10 |
The details of any documents that are considered relevant and
necessary A full statutory disclosure of all documentation held by Welsh
Ministers relating to the site. This to include Ministers’ and officials’
consideration of environmental and legal factors taken into account prior to
decision, records of consultations with public bodies and dealings with
Kemble. In particular the Society wishes to see evidence that the s62 duty
has been fulfilled. |
|
11 |
The address for reply and service of court documents Ty Hyll, Capel Curig, Gwynedd LL24 0DS |
|
12 |
Proposed reply date May 23, 2008. In any event we would ask that a reply is made before the lease
is signed. Kemble have made public statements that they expect to be on the
site in early June. |